The method
Before using the result
- Target ACH must be selected independently for the actual use. This calculation does not establish compliance with an occupancy-specific ventilation standard.
Worked examples
These original training examples illustrate the method for BOMI Systems Maintenance Technician (SMT). Use the matching “Load example” button above to explore a variation; example values are not equipment settings or prescribed criteria.
1. Worked example
Convert a documented facility design ACH target into a flow requirement. The calculation makes the target visible without claiming it satisfies an occupancy-specific ventilation standard.
- Room length
- 10 m
- Room width
- 8 m
- Room height
- 3 m
- User-supplied target ACH (h⁻¹)
- 6
- Source of target
- Worked example only; enter the applicable design target
- Volume = 240 m³.
- Flow = 240 × 6 / 3600 m³/s.
- Volume: 240 m³
- Calculated flow: 0.4 m³/s
- Target source: Worked example only; enter the applicable design target
2. Comparison example
Compare a different supplied condition using the same method. For Facility Cert Exam, the important check is that the input meaning, units and method assumptions still match the problem.
- Room length
- 10 m
- Room width
- 8 m
- Room height
- 3 m
- User-supplied target ACH (h⁻¹)
- 4
- Source of target
- Worked example only; enter the applicable design target
- Volume = 240 m³.
- Flow = 240 × 4 / 3600 m³/s.
- Volume: 240 m³
- Calculated flow: 0.2666667 m³/s
- Target source: Worked example only; enter the applicable design target
Check your understanding
1. Which relationship is used?
Required flow = room volume × target ACH / 3600.
2. Which assumption should you check first?
Target ACH must be selected independently for the actual use. This calculation does not establish compliance with an occupancy-specific ventilation standard.
3. How should you verify a different unit system?
Convert every input to the displayed calculation units first. Equivalent physical inputs must give equivalent results; a unit label alone does not convert a number.